I-35 Utility Relocation and Change Order

Denton

Summary

A $2.7 million change order was approved for utility relocations along I-35 due to delayed easement acquisitions on a UNT intramural field. Staff noted that TxDOT pushed the timeline, but 100% reimbursement is anticipated.

At a glance

Total mentions
1
Last 30 days
0

Last discussed May 18, 2026.

Impact analysis

💰Financial impact

$2,722,204.25 increase, expected to be 100% reimbursed by TxDOT.

✅Who benefits

Motorists and the regional transportation network through coordinated state and municipal infrastructure upgrades.