Summary
A $2.7 million change order was approved for utility relocations along I-35 due to delayed easement acquisitions on a UNT intramural field. Staff noted that TxDOT pushed the timeline, but 100% reimbursement is anticipated.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed May 18, 2026.
Impact analysis
$2,722,204.25 increase, expected to be 100% reimbursed by TxDOT.